Bannerman's Etango uranium project reaches 92% of bulk earthworks

More than 560 contractors are on site in Namibia as the company edges toward a fourth-quarter investment decision

27 July 20262 min read
Bannerman's Etango uranium project reaches 92% of bulk earthworks

Bannerman Energy has reported major construction progress at its Etango uranium project near Walvis Bay, Namibia, with bulk earthworks now 92% complete and more than 560 contractor personnel working on site. The company said the project has recorded over 1.1-million hours worked without a lost-time injury.

Concrete and pipeline work advancing

Roughly 60% of the concrete required for critical dry-plant infrastructure has been cast, and a water pipeline serving the site is 87% complete, Bannerman said. The Australian-listed developer described early works as on schedule and within budget, a notable claim for a greenfield uranium project of Etango's scale.

Financing nearly settled

Etango's construction has been underpinned by a strategic investment of up to $321.5-million from China's CNNC Overseas Limited, which is taking a stake in a jointly owned development company alongside Bannerman. The company said it expects to take a final investment decision shortly after that financing transaction completes, which it anticipated in the following quarter — pointing to an FID in the fourth quarter of calendar 2026.

Why Etango matters for Namibia

If it proceeds, Etango would become Namibia's fourth producing uranium mine, adding to Rössing, Husab and the recently restarted Langer Heinrich. Namibia has become one of the world's most important uranium-mining jurisdictions, with Chinese state-linked capital playing a central role in unlocking new supply as global utilities lock in long-term contracts to secure fuel for expanding nuclear fleets.

What happens next

With early works largely funded and progressing, the milestone that matters most now is the formal FID. Once taken, Bannerman has said full-scale construction can begin quickly given the advanced state of the earthworks, pipeline and concrete programmes already under way — putting first production potentially within reach before the end of the decade.

Sources

Photo: Walvis Bay port in Namibia, near Bannerman Energy's Etango uranium project. Ji-Elle, Wikimedia Commons, CC BY-SA 4.0.

Was this useful?

Advertisement

Discussion

Comments are moderated. Keep it on topic.

Loading comments…

Keep reading

More from MiningWrap

The MiningWrap Brief

The whole sector in one weekly read.

Deals, policy and markets — every Thursday.